BCC Bus Wash Upgrades
|
Design and installation of water recycling plants.....
|
|
read more
|
|
|
Lower Molonglo Water Quality Control Centre Secondary Treatment Facility Augmentation Project
|
Upgrade of the secondary treatment facilities including the construction of three secondary clarifiers, RAS pumping stations, anoxic tanks, level control structure, MCC building, pipelines, methanol dosing facility, MLR pumping stations, Bioreactor modifications, access roads and associated works.
|
|
read more
|
|
|
|
Fyshwick Effluent Reuse Plant
|
Upgrade of the existing plant, the plant provides recycled water to irrigate the grounds of Duntroon....
|
|
read more
|
|
|
Tin Can Bay, Rainbow Beach and Cooloola Cove Sewage Treatment Plants
|
Construction, testing and commissioning of three sewage wastewater treatment plants....
|
|
read more
|
|
|
SP68 Gravity System Mechanical Installation
|
Jan 09 - Apr 09
BMP TENIX ALLIANCE
Construction consisted of a single circular well with a dividing wall separating the wet well from the dry well. Three dry mounted submersible pumps were installed within the dry well with lift and ladder access for maintenance personnel. A control building constructed above the well to house electrical switchgear, odour control facilities, SCADA control interfaces and basic amenities. Scope includes: Main pumps, sump pump, installation of suction, riser and valve pit pipework incl pipe supports and Testing.
Value: $300 000
|
|
|
|
|
Goodna Sewage Pump Station
|
Dec 06 - Feb 08
IPSWICH CITY COUNCIL
Construction of a 8.5 metre diameter pump well, dry valve pit, flowmeter pit, electrical control building, standby generator, odour control equipment, site filling and retaining wall construction, site pipe-work, access roadway extension and ancillary works.
Value: $8 600 000
|
|
|
|
|
Belmont Waste Water Treatment Plant Works Stage 3
|
Oct 06 - 07
HUNTER WATER CORPORATION
The stage 3 upgrade increased the nominal capacity of the plant to 115,000EP. This work involved augmentation of the aeration capacity and tankage, new improved grit removal facilities, new aerobic digesters, a new clarifier, new sludge handling facilities, a major upgrade of the power and controls to the plant and a number of other improvements.
Value: $20, 100 000
|
|
|
|
|
Marsden Sewerage Pump Station
|
Dec 06 - May 07
LOGAN CITY COUNCIL
Construction of a gravity sewer and rising main including concrete wells, pump station pits and creek crossing. Supply and installation of submersible pumps, concrete manholes, electrical works and telemetry for pump station, kerb and channel and fencing.
Value: $2 000 000
|
|
|
|
|
Sewerfix Pumping Stations Upgrade Program - Stages 1- 2 & 33
|
Mar 02 - Jun 04
BTC GROUP
Upgrade of 30 sewage pumping stations - including construction of overflow structures, valve chambers and access pits. Installation of pipework to new structures and replacement of pipework and pumps to existing wet wells.
Value: $8 000 000
|
|
|
|
|
Jamberoo Pump Station
|
Jul 04 - Oct 04
PSPAT
Upgrade of sewer pumping station SPS779 - Earthworks and concrete works for sewer pump station. Construct temporary access road.
Value: $230 000
|
|
|
|
|
Warriewood STP
|
2004
SYDNEY WATER CORPORATION
Upgrade of digester system, heat exchanges and compressors.
Value: $2 000 000
|
|
|
|
|
Rickard Road Warrimoo
|
Jul 03 - Jan 04
JOHN WYCLIFFE PUBLIC SCHOOL
Construction of SPS including earthworks, structure, mechanical and electrical.
Value: $550 000
|
|
|
|
|
Mornington STP
|
2004
SOUTH EAST WATER LTD
Detail design and construction of inlet works upgrade.
Value: $2 100 000
|
|
|
|
|
Richmond Pump Stations 3,4,5
|
Apr 03 - Oct 03
UNIVERSITY OF WESTERN SYDNEY
Construction of 3 new pump stations, includes pipe laying and electrical work.
Value: $250 000
|
|
|
|
|
Mt Victoria Pump Station
|
Jun 03 - Dec 03
SYDNEY WATER
Construction of new pump stations including wet wells, valve chamber and man hole. Installation of pipe work and pumps and construction of driveway and turning bay.
Value: $400 000
|
|
|
|
|
Shellharbour STP
|
2003
SYDNEY WATER CORPORATION
Design and construction of optimisation system and digesters.
Value: $ 2 500 000
|
|
|
|
|
Mt Riverview STP Demolition and Rehabilitation
|
Apr 02 - Jun 04
SYDNEY WATER
Demolition of disused sewage treatment plant, regrading site and planting with native vegetation.
Value: $600 000
|
|
|
|
|
Ballarat WWTP
|
2002
CENTRAL HIGHLANDS WATER
Supply and installation of a screenings plant.
Value: $ 625 000
|
|
|
|
|
Malabar STP
|
2001 - 2002
SYDNEY WATER CORPORATION
Design and construction of scum and gas handling facility. Upgrade of chemical storage system bund, conveyors and process equipment.
Value: $1 600 000
|
|
|
|
|
Eastern Treatment Plant , VIC
|
2001
MELBOURNE WATER
Upgrading of screenings, classifiers and dewatering plants.
Value: $3 000 000
|
|
|
|
|
Millmerran STP Augmentation Civil Works
|
Aug 00 - Jan 01
MILLMERRAN SHIRE COUNCIL
Construction of a reinforced concrete inlet chamber, primary sedimentation tank, trickling filter, secondary sedimentation tank and sludge digester, pipelines, effluent storage pond, general earthworks and ancillary works.
Value: $550 000
|
|
|
|
|
Quakers Hill STP - Sludge Handling Facilities Upgrade
|
Jul 99 - Dec 99
John Young
Design and construct all civil works associated with the upgrade of the Quakers Hill Sewage Treatment Plant Sludge Outloading Facility.
Value: $200 000
|
|
|
|
|
Rouse Hill STP - Noise and Odour Barriers
|
Jan 98 - Nov 98
CLM EXCAVATIONS
Noise walls and odour barriers at Rouse Hill Sewage Treatment Plant.
Value: $150 000
|
|
|
|
|
Malabar STP
|
1997 - 1999
SYDNEY WATER CORPORATION
Upgrade of ventilation system, design and construction of screenings disposal facility, design and construction of hot water generation system, design and construct filtered effluent system.
Value: $4 500 000
|
|
|
|
|
St Marys STP - Upgrade
|
Jan 96 - Nov 96
CLM EXCAVATIONS
Formwork and concrete placement at a sludge storage facility at St Marys Sewage Treatment Plant.
Value: $300 000
|
|
|
|
|
North Head STP
|
1995 & 1998
SYDNEY WATER CORPORATION
Installation of screens and grit handling facilities. Installation of raw sludge pump cooling water system and heat exchangers.
Value: $690 000
|
|
|
|
|
Rouse Hill STP
|
1994
JOHN HOLLAND and SEPA
Installation of pipework, clarifiers and filters.
Value: $550 000
|
|
|
|