Wollongong STP Biosolids Handling & Odour Control Facility
info_current1
Title
Wollongong STP Biosolids Handling & Odour Control
Division
Process
Client
Sydney Water Corporation Ltd
Client Contact
Mile Purdevski Ph: 02 4225 2624
Current Status
90%
Project Start Date
August 2009
Construction Period
52 Weeks
Project Description
Demolition of old and construction of new Odour Control Facility and extension of biosolids room including earthworks, structural works. Design fabricate and install all FRP ductwork. Also design, fabricate and install nutrient transfer, storage and dosage systems.
Complex Challenges
Working within and around a brownfield site.
Contract Type
Lump sum
Value
$8 000 000
Consultants / Designers